House looks almost ready to live in doesn't it? :p We had a "Pre-Plaster" inspection a couple of weeks ago and there were 12 more defects that needed rectification/justification. Money well spent on the inspector we have to say but frustrating to find out about defects. However that hasn't slowed the progress on the house as you can see the front facade render has been applied, although one of the defects require the brick wall on the front porch to be pulled down and rebuilt! Plaster walls have also been put in even though there are still some outstanding timber frame issues, and we are also yet to find out if our wall batts (insulation) have been put in. Will update more about it after the builder has rectified things and a re-inspection performed.